Projects & Development

BioTech is Powering Up

Scaling RNG Across America

Current Pipeline:

BioTech currently has three plants under contract, two under permitting review with the state, with groundbreaking on Plant #1 by end of Q1 2026

With a 20 month construction period, this sets up BioTech to bring online 4.5 BCF in 2028 for the first 3 plants

The first 4 plants are targeted for Feedlot Manure, an underutilized feedstock in the U.S.

Plant 5 will be the first rollout of the largest RNG plant design using 100% lignocellulosic material, an RNG feedstock that is not currently used in the U.S.

Strategic Locations:

Plant 1, Nebraska
1.5 BCF, 25 MWe
Breaking Ground in March 2026

Plant 2, Nebraska
1.5 BCF, 25 MWe
Permit under review by the State

Plant 3, Iowa
1.5 BCF, 25 MWe
Permit submittal in Q1 2026

Plant 4, Texas
2.0 BCF, 33 MWe
Contract and Design/Permitting to commence in Q1 2026

Plant 5, North Dakota
4.0 BCF, 66 MWe
Land agreement and contract to commence Q1 2026

Plant 6, California
2.0 BCF, 33 MWe
Land and gas contracts executed; feedstock and technical work starting Q2 2026

Built for Growth